ivsenroute
Senior Member
- Location
- Florida
What method do you use when installing the grounding electrode system where the disconnects are grouped together?
Do you run the GEC from the closest panel to the electrode then using the internal terminal bars of the disconnects connect the other ones the the first one like a daisy chain?
Do you run the GEC from the farthest disconnect then crimp the other grounds coming from the other panels to the GEC like it is a trunk line (tap method)?
Install a nice thick 1/4 grounding plate (busbar) at a central location?
Another method?
What is popular in your area.
Do you run the GEC from the closest panel to the electrode then using the internal terminal bars of the disconnects connect the other ones the the first one like a daisy chain?
Do you run the GEC from the farthest disconnect then crimp the other grounds coming from the other panels to the GEC like it is a trunk line (tap method)?
Install a nice thick 1/4 grounding plate (busbar) at a central location?
Another method?
What is popular in your area.
Last edited: