I need a clarification on Article 250.32. I have a 100 amp 1 phase sub panel ran to a detached building 225' away from the house. No water line or gas line ran to the new building. I ran 3 lines to the building, drove two ground rods and treated the sub panel as a new service. The Article say you should run a Equipment ground. with the feed conductors, but under the exceptions is says the 4 wire is not needed if these conditions are met, which they all are. Please give me your input. If there was an issue where a fault would occur at the detached building I would not want it going back to the house, but going to the driven grounding rods.