Hi Folks,
I've ran into a situation with my local building official, and I would love some input on the subject matter.
Scenario:
400Amp service being fed by (2) Sets of (4-wire) 3/0 Cu.
Based off NEC 250.66 and the cross sectional area, should the ground be based on number of sets, thus (2) 3/0 Cu.
OR
Should it be based on total wires, thus (8) 3/0 Cu.
Any and all input would be appreciated.
I've ran into a situation with my local building official, and I would love some input on the subject matter.
Scenario:
400Amp service being fed by (2) Sets of (4-wire) 3/0 Cu.
Based off NEC 250.66 and the cross sectional area, should the ground be based on number of sets, thus (2) 3/0 Cu.
OR
Should it be based on total wires, thus (8) 3/0 Cu.
Any and all input would be appreciated.