sixstrings
New member
I am building a 1200 amp 3 phase 120/208 service with 6 meters. I am concerned I may not know exactly how to ground this set up. The risers come into a tapbox to which the meter cans are attached by bus bars. I have three parallel 500 kcmils cables for each phase and the neutral. each phase comes in through a separate riser. anyway I am unsure exactly how to ground this service. Help!