I have a question as to which way would be best to ground this service that we are working on.There was no ufer ground installed when the slab was poured.I have an 800 amp service with the main outside. They recently added a bath on another floor. the plumbing pipe is not in but i belive they are going to bring the pipe trough the wall on the third floor.Since this particular part of the building will also be under ground, can i bring my ground wire out trough an extra 4inch pipe run it along the outside of the building and then back in to catch the pipe?Also since this wire will be run about 100 feet can i also use it as a supplemental ground for my dist panel inside the building? If there is a better way i would gladly like to hear it.Also can i chop some concrete and go to the rebar?