In this area the POCOs will only except RMC up the pole with a large radius RMC sweep, some want 10 more feet of RMC underground.Originally posted by tom baker:
A change for the 2002 NEC allows metal raceway containing service entrance conductors to be bonded to the utility service neutral at the pole, see 250.102(E) exception. It is usually easier to use sch 80 PVC on a pole, or fiberglass in cold climates.