ivsenroute
Senior Member
- Location
- Florida
This situation was discussed today (although briefly) concerning grouping of disconnects on townhouses and duplex units. Still nothing concrete or clear from the discussion at our IAEI annual spring seminar today.
Here is one situation:
A duplex, up and down with 1 service drop to a 2 gang meter base on the left side. Can you run from the meter to the basement for the lower unit with a main panel/disco then run from the 2nd meter outside the building up to the 2nd floor unit with another main panel/disconnect?
What is your NEC opinion?
Here is one situation:
A duplex, up and down with 1 service drop to a 2 gang meter base on the left side. Can you run from the meter to the basement for the lower unit with a main panel/disco then run from the 2nd meter outside the building up to the 2nd floor unit with another main panel/disconnect?
What is your NEC opinion?