cottora
Senior Member
- Location
- Atlanta, GA
We are having issues with the local POCO being able to deliver service in time because of their lead time on a 1MVA transformer. We can change service type to Primary and lower our bill; however, we must install 2,000' of underground (or overhead) and set/install the transformer. We have a delivered price for the transformer but I don't have a clue what this type of labor/installation may cost. Any guestimates on cost would be greatly appreciated (to be clear, if we go this route, we will hire a licensed contractor). I do get that we now have responsibility for the equipment but just trying to kick around some ideas.
Thanks again!
Thanks again!