Dustin Foelber
Senior Member
We are replacing an existing switchboard on a project to accommodate (16) added sub-feeds to the (8) existing. All are 2 1/2" conduits. I am having a difficult time figuring out if our proposed application to put a large gutter/pull box above the gear is NEC approved. Also difficult to determine size.
I have attached a drawings showing our application. Any feedback is much appreciated. Thanks
I have attached a drawings showing our application. Any feedback is much appreciated. Thanks