Knuckle Dragger
Master Electrician Electrical Contractor 01752
- Location
- Marlborough, Massachusetts USA
- Occupation
- Electrical Contractor
I was helping out a fellow electrician this week with meter assembly replacement. The pad mount transformer is feeding a four gang pedestal mounted meter socket on the same concrete pad (the line and all four loads are underground).
There were a lot of issues with this one job but I want to deal with one just to make a long story short.
The original neutrals were bugged together I am talking the 350mcm and all four 4ott cable to make one big splice that never made it into the meter sockets, they were spliced in a can that made up the pedestal so only the two 4ott loads went into a 2inch pvc conduit. I would say the total distance from the meter socket load and the neutral wad was 22 inches.
My question is what kind of harmonics issue are we dealing with?
Footnotes:
Each load feeds a 200amp residential panel, electric heat, hot water, a/c stove etc.
Thanks for your help!!
There were a lot of issues with this one job but I want to deal with one just to make a long story short.
The original neutrals were bugged together I am talking the 350mcm and all four 4ott cable to make one big splice that never made it into the meter sockets, they were spliced in a can that made up the pedestal so only the two 4ott loads went into a 2inch pvc conduit. I would say the total distance from the meter socket load and the neutral wad was 22 inches.
My question is what kind of harmonics issue are we dealing with?
Footnotes:
Each load feeds a 200amp residential panel, electric heat, hot water, a/c stove etc.
Thanks for your help!!