Neither did I.I didn't see anywhere in the code that tells me not.
I think that once it passes into the footprint of the building walls it is "within the building. Unless buried Deep enough or encased in concrete."Seems like direct burial is ok. What I don't know is 353.12(2) says it can't be used "within a building". Does that mean that as soon as the conduit passes the grade beam, that it needs to be ended even if it comes in a crawl space?