Energy-Miser
Senior Member
- Location
- Maryland
When we do a residential heavy up, once our inspection for it is done, then the power company (BGE in our area) would get the word from the inpector's office and would schedule their work to change the connection from temporary to permanent. This is how it used to be done. Recently we have found out that they don't schedule the permanent connection automatically anymore, and that we will need to take action, except that no one at the BGE offices can tell us what we need to do. Can any of Maryland contractors reading this, tell me if you know how we need to schedule this with BGE? You can PM me if you want, or post your response here. Thanks in advance. e/m.
(sorry if you see this more than once, I had originally posted it by mistake under calculation / engineering, but do not know how to delete it from there).
(sorry if you see this more than once, I had originally posted it by mistake under calculation / engineering, but do not know how to delete it from there).