KD4315
Member
- Location
- San Francisco, CA
I was estimating a job last week that had some temporary power requirements. We excluded it but for my own knowledge I'm curious about calculating this service.
The existing site has 208 3 phase power to it. The GC's man lift and crane operate on 480. There is a 1000A 208V Temp board on site. The crane needs 400A service and the man lift needs 200A service. How big of a transformer and temp panel do I need to run both of those?
The existing site has 208 3 phase power to it. The GC's man lift and crane operate on 480. There is a 1000A 208V Temp board on site. The crane needs 400A service and the man lift needs 200A service. How big of a transformer and temp panel do I need to run both of those?