Ran into another installation yesterday where the high leg was landed on Center position on the panel AND center position on the meter base. Had to call another electrician and explain why this is wrong, again...
I’ve seen them where they were landed on C position on Meter base and C position on panel, and I made it a point to call the electrician to explain why this is wrong, only to have him tell me the inspector passed it, and to hook it up. Then gets mad when I refuse because I don’t want to blow HIS equipment up...
I had an instructor in a CE class say some utilities want them on the right side, some wants them on the left side, and the utilities need to make their mind up.
I can’t get some to understand the high leg on C phase(right side) of the meter base is a metering issue and must be done that way to meter correctly.
Code says where to land it in the panel, but I still see it marked orange, in the C phase position, and passed inspection.
I don’t mind moving it to the correct position, but then I’m liable should something go wrong down the line because I changed the wiring...
Question... connect it if it passed inspection, or continue to call? Naturally if it isn’t in the correct place on the meterbase it has to be changed before we connect, because it won’t meter correctly.
I’ve seen them where they were landed on C position on Meter base and C position on panel, and I made it a point to call the electrician to explain why this is wrong, only to have him tell me the inspector passed it, and to hook it up. Then gets mad when I refuse because I don’t want to blow HIS equipment up...
I had an instructor in a CE class say some utilities want them on the right side, some wants them on the left side, and the utilities need to make their mind up.
I can’t get some to understand the high leg on C phase(right side) of the meter base is a metering issue and must be done that way to meter correctly.
Code says where to land it in the panel, but I still see it marked orange, in the C phase position, and passed inspection.
I don’t mind moving it to the correct position, but then I’m liable should something go wrong down the line because I changed the wiring...
Question... connect it if it passed inspection, or continue to call? Naturally if it isn’t in the correct place on the meterbase it has to be changed before we connect, because it won’t meter correctly.