Need to figure our feeder sizing for installing heat pumps in 165 hotel rooms. Hotel has 2000 amp 120/208 volt 4-wire service. Each unit is 208-volt single phase and draws 11.4 amps. 424.3 mentions a continuous load. Do i really take these at 100%? something doesn't seem right? Thanks.