C cgilland New member Nov 2, 2007 #1 Is there a demand factor or diversity factor for determining the total service size on a hotel project?
Is there a demand factor or diversity factor for determining the total service size on a hotel project?
roger Moderator Staff member Location Fl Occupation Retired Electrician Nov 2, 2007 #2 Read article 220. Roger
bob Senior Member Location Alabama Nov 5, 2007 #3 cgilland said: Is there a demand factor or diversity factor for determining the total service size on a hotel project? Click to expand... Table 220.42 gives your the lighting requirements. There is not much that will have diversity. A/C 100%, kitchen 100%, Hot water 100%. What else is there?
cgilland said: Is there a demand factor or diversity factor for determining the total service size on a hotel project? Click to expand... Table 220.42 gives your the lighting requirements. There is not much that will have diversity. A/C 100%, kitchen 100%, Hot water 100%. What else is there?