I have a 38 FT run of 2-1/2 IMC from my disconnect outside to my first enclosure inside the building.
It has (3) standard radius 90s and (1) 30 for a total of 300 degrees of bend.
This is a 200A 3P High leg Delta installation.
The pull consists of:
(4) 3/0 conductors, 3P + Neutral
(1) #4 EGC
For referencce from the fill chart I am allowed (7) 3/0 conductors in 2-1/2 IMC.
From your guys experience how hard will this pull be to be done by hand?
Big thanks