Re: How long to wait to get paid
Originally posted by bradleyelectric:
can you show me how you word your contract to reflect this?
Which part?
Are you trying to come up with your own custom subcontract? Or is it more of a combo proposal/contract that a homeowner signs to accept your bid, authorize you to do the work and guarantee to pay you?
Are you working as a sub to a GC or directly with the owner?
What type of work?
I end up having to deal with a number of different contracts. The wording can get pretty tricky at times.
As a sub, if it's a small project, I usually try to use the AGC Document No. 603 (Std. short form) as a starting point, modify it's wording (quite a bit) and add about 5 listed exhibits. This is for smaller commercial projects. For larger projects I usually use the AIA subcontract form or the AGC full subcontract form as a starting point.
One of the exhibits is "Payment Provisions". In it, I describe how payments are to be made. That is where you would want to list your payment milestones.
For instance in a residential setting:
Payment of subcontract amount:
30% due within 3 calendar days of execution of this subcontract.
30% due within 3 calendar days of rough-in inspection.
30% due within 3 calendar days of [whatever event triggers approval to turn on power]. Note that permanent power will not be energized until this payment has been received.
Remaining 10% due within 3 calendar days after Substantial Completion of the Subcontract Work, less $25 for any light fixture, ceiling fan, switch, receptacle or other electrical device that cannot be completed at that time because of lack of equipment or because some portion of the construction is not yet sufficiently completed. (etc, etc.)
A few payment provisions that I've used lately:
"Payments shall be made by the Contractor to the Subcontractor when due, regardless of whether the Contractor has or has not received a corresponding payment from the Owner for the Subcontractor's work."
"No retainage shall be withheld or deducted from any payment"
"Final payment of the entire remaining contract balance shall be made within seven (7) calendar days of substantial completion of the subcontract work or of the suspension of significant building progress by the contractor, whichever is earlier" (of course "significant building progress" can be open to interpretation)
None of this may fit your situation or be very helpful to you, but maybe it will give you some ideas.
Developing contract wording can be very tricky. It needs to fit the type of work you are doing and who you are working for. It is also affected by your state laws. If you're fairly new to doing this, then a little time with a good
construction attorney is worthwhile. Make sure you use an attorney that specializes in construction law.
The first thing to do is to write down a complete outline (list) of everything that you would like for your contract to accomplish for you. Then figure out the wording that will accomplish it -- probably initially with legal help.
Bear in mind that one of the hurdles is getting the other side to agree with you over contract requirements. One of the methods I use is to ask them to explain what's wrong with what I'm asking for, and then ask them things like: "Well, sir, does that mean that you don't intend to pay me? Then what's your objection to saying in writing how you will pay me? If you were me, wouldn't you want it in writing, too? What happens if you get run over by a bus... whoever completes this project won't know what you promised me." etc, etc.
I'll be glad to help you in any way I can, but I certainly don't claim to be an attorney. (Insert all applicable disclaimers here
)
[ August 04, 2005, 02:52 AM: Message edited by: tx2step ]