bjp_ne_elec
Senior Member
- Location
- Southern NH
Install new dedicated 20A circuit in finished basement Family Room with 20A GFCI - length for HR approx. 50' from panel. Back of wall is accessible - would use existing Romex, disconnecting from present circuit, buttoning up existing circuit, and then feed existing box with new 12/2. Install new 20A GFCI and cover.
Install new dedicated 15A HR (approx. 80') to series of 15A wall outlets - two of which are exposed (they are accessible on back side of Family Room wall as the backside is open to the unfinished basement), and would feed with new 14/2 Romex. Three other outlets would use existing wire (assuming ground it installed - some wiring in house on other circuits has been found to contain the older Romex with no EGC). Have to pick up a common point and feed these three (3) receptacles of new circuit (present installation happens to be fed with a 20A breaker, and when checking the existing wiring, noted cicuit only had 14/2 run to panel as well as feeding each receptacle.
Note: Drilling floor joists for new HR's is part of the incurred work.
Now - having that price, let's make an additional assumption, and that is you discover no EGC in existing installed ROmex, so you have to work a GFCI in to accomadate these receptacles with no EGC.
I want to see if I'm "in the ball park" on my pricing.
Thanks,
Dave
Install new dedicated 15A HR (approx. 80') to series of 15A wall outlets - two of which are exposed (they are accessible on back side of Family Room wall as the backside is open to the unfinished basement), and would feed with new 14/2 Romex. Three other outlets would use existing wire (assuming ground it installed - some wiring in house on other circuits has been found to contain the older Romex with no EGC). Have to pick up a common point and feed these three (3) receptacles of new circuit (present installation happens to be fed with a 20A breaker, and when checking the existing wiring, noted cicuit only had 14/2 run to panel as well as feeding each receptacle.
Note: Drilling floor joists for new HR's is part of the incurred work.
Now - having that price, let's make an additional assumption, and that is you discover no EGC in existing installed ROmex, so you have to work a GFCI in to accomadate these receptacles with no EGC.
I want to see if I'm "in the ball park" on my pricing.
Thanks,
Dave
Last edited: