How to bid a "70% complete set of prints" project?

Status
Not open for further replies.
Thanks again for all of your responses.
It's a big warehouse with temperature control and storage and we'd just be bidding the controls part.
The missing part for me is that no one is saying what "70%" means. Does it mean 90% of the structural is complete, 70% of the mechanical is done and only 10% of the controls are done, etc. etc. etc.

We'll figure something out.
Can you look at the available 70% of prints cover and work from there - obviously with the caveats already suggested?
 
A really costly trend we see now days is bidding off the first set of plans, while the plans are still in plan check. We had one guy pick up his plans and then called for rough electrical the next day. I asked him where his three insta hot circuits were, one being 60 amps, I also told him that he would have to remove the panel that he had in the rated wall, that was not identified on the original plan check and several other things.

He wanted to argue that those things weren't on his plans and I conceded that he was probably right, but they were on the approved plans.

Had one guy install ever receptacle box to low for ADA, that's a costly mistake. Now should he have known how high to install them, probably, but the plans called for 12" to the center, before I had it corrected.
 
Status
Not open for further replies.
Top