Alfont1120
Member
- Location
- Dighton, MA
- Occupation
- Electrical Project Manager/Journeyman Electrician
Good Afternoon,
I am trying to determine what the load will be per phase for the system we have installed here (not yet energized). We have a 3-phase, 208 volt, 400 amp fusible disconnect with (4) fused disconnects tapped off of it. Each disconnect feeds a panel with the following main breakers: 200A, 150A, 150A and 100A. We'll call them panels 1-4 in that order. These panels are installed inside of mobile office trailers. We've already done load calculations for all 4 trailers so for the sake of this question, let's just assume the calculations are correct and panels 1-3 will draw 102.25 amps, with panel 4 drawing 80.95 amps. If panel 1 his fed with phases AB, panel 2 with BC, panel 3 with AC and panel 4 with AB, what would the total draw be per phase? I am trying to determine how out of balance our system will be and if it will be a potential issue/reason for the inspector to fail us. That being said, is there any standard or mention in the NEC what the allowable max deviation against the average current can be?
Thank you for any help in this matter
I am trying to determine what the load will be per phase for the system we have installed here (not yet energized). We have a 3-phase, 208 volt, 400 amp fusible disconnect with (4) fused disconnects tapped off of it. Each disconnect feeds a panel with the following main breakers: 200A, 150A, 150A and 100A. We'll call them panels 1-4 in that order. These panels are installed inside of mobile office trailers. We've already done load calculations for all 4 trailers so for the sake of this question, let's just assume the calculations are correct and panels 1-3 will draw 102.25 amps, with panel 4 drawing 80.95 amps. If panel 1 his fed with phases AB, panel 2 with BC, panel 3 with AC and panel 4 with AB, what would the total draw be per phase? I am trying to determine how out of balance our system will be and if it will be a potential issue/reason for the inspector to fail us. That being said, is there any standard or mention in the NEC what the allowable max deviation against the average current can be?
Thank you for any help in this matter