1) The Medium Voltage cable is manufactured according to IEC and it is armored (GSWA - Galvanised Steel Wire Armored)
2) The breaker (Medium Voltage NEMA Switchgear lineup) feeding the above cable is manufactured as per NEMA
3) The Power cable sizing is done per IEC
If I have to size the equipment grounding conductor (PE in IEC land), what is the code I have to follow?
If NEC - I would use NEC 250.122
or
If IEC - What is the code/rule I have to follow