Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
Hello. Have new construction building with new underground incoming as shown below to a 1200A switchboard.
Need to setup a temp service(about 400A) but not sure exactly how it would more than likey be done in field.
The one set #500 for 1200A is obviously wrong.
1. Would they more than likely install the permanent before hand and only use some of the sets?
2. Would temp conductors be run from the utility manhole or property line box?
Thanks.
'
Need to setup a temp service(about 400A) but not sure exactly how it would more than likey be done in field.
The one set #500 for 1200A is obviously wrong.
1. Would they more than likely install the permanent before hand and only use some of the sets?
2. Would temp conductors be run from the utility manhole or property line box?
Thanks.
'