For the most part our inspectors work with the ec`s in the area as far as time goes.Most have direct connect so we can call in the A.M. and set an aprox. time to meet them.It usually works out for the best.If they get tied up they will call and let us know.
The change of inspectors in an area can be a pain,some require this and some require that.What I try and do is install to the most stringent inspectors wishes that way all bases are covered.
Inspectors get and have the right to get p`d when an inspection is called and the job is not ready.Here an inspector usually rolls several inspections daily due to work load and time.So when they go to an inspection that isn`t ready.That just means they wasted thier time that could have been better utilized.
Now on the EC`s side of the fence:
Some inspectors interpet gray code areas in a way that makes it difficult to comply.Take the requirement for a light and a switch in a hall.What determines what a hall is.I have had inspectors require a seperate light in a 3 ft X 3 ft. barrel arch that led into a bedroom.Didn`t matter that there was a recessed can 1 ft. off the wall centered over the arch.We had to add a recessed can in a arch that was 7 ft AFF.He called it a hallway.But at the same time he measured wall spacing from the doorway in the archway to comply with the 6 ft. rule.Its a hall for lighting but not a hall for wall spacing ???
Protection from physical damage is another one.What constitutes not protected ??? Case in point block home,furring across the top of the block.Notched and kick plated but the furring is like 1 in below the top of the block.Inspector cites 300.4 D.Drywall when installed on the ceiling can damage the NM,so install more kick plates.We comply,then one day a service call.HO getting shocked from SGD.Sure enough Door,Foil vapor barrier,corner bead energized .Why??? the kick plate we were made to add above the furring had cut into the NM when ceiling board was installed.Would have been better the other way.Now all of a sudden don`t add them any more ???
1/4 in. set back.We trim and complete the trim.Sometime between the finish and the inspection.Tile installer comes in the kitchen and tile the counter wall.Now we get cited for 1/4 in set back,no spark guards.
Panel bond screw loose.Inspector cranks down with all his might to try and get the screw to turn.But the screw has a specified torque value,I think the one we were using had a value of 35 in. lbs.So where is his torque screw driver to determine that the screw was not torqued to proper value.
In use covers.The determination of which GFCI exterior receptacles that require them is on a inspector to inspector basis.Some give a definitve distance under an over hang while some just say I feel it can get wet in a driving rain.
A/C max.bkr. sizing.Some say that it must be fused at the max. size while others say just make sure its between min. ampacity and max. bkr size.
Useable wall space.Now thats a good one.Case in point .Family room that leads into a master bedroom.The door that leads into the bedroom is flush with the exterior wall that has a sliding glass door.Absolutly no wall space for a receptacle but due to building codes in this area a 16 ft. SGD has to have fixed panels on the sides.No place for a wall mounted receptacle at all,but since there is a fixed panel a receptacle is required.Inspectors note need receptacle GOOD LUCK !!!!! So now HO has a floor receptacle on a carpeted floor slap in the doorway of the bedroom.So now when they wake up in the morning they stub there foot on a receptacle they never wanted in the first place.
Consistancy that is what really needs to be addressed.I`ve tried to do my best to find out what each inspector wants but sometimes they vary so much it`s frustrating.