AC\DC
Senior Member
- Location
- Florence,Oregon,Lane
- Occupation
- EC
he Said for a temp these won't work https://rexel-cdn.com/products/12248413specshturl.pdf?i=78820FB5-A252-486E-9707-623DD6FC7930
he said they don't meet 406.9.b1
He said my offer does not count until stem wall is pored even though footer is poured and the rebar was marked good as a GE
he then said
Electrical equipment adjacent to or that will be attached to the building shall not be energized until the roof sheathing has been installed 110.3A9, 110.27B, 408.20
I framed it 1" from the building so contractor can Frame building then we can remove my wood and just slap it in place---- its all 3R What is his problem----
does he have a leg??? Am I wrong?
he said they don't meet 406.9.b1
He said my offer does not count until stem wall is pored even though footer is poured and the rebar was marked good as a GE
he then said
Electrical equipment adjacent to or that will be attached to the building shall not be energized until the roof sheathing has been installed 110.3A9, 110.27B, 408.20
I framed it 1" from the building so contractor can Frame building then we can remove my wood and just slap it in place---- its all 3R What is his problem----
does he have a leg??? Am I wrong?