The vast majority of the site I am at is designated Class 1 , Division 2 with a few Class 1, Div 1 locations. I am just curious as to how other sites do maintenance on classified equipment - are there separate PMs or are they incorporated into other maintenance interventions? For me every single transmitter would be classified. So for example, I would say when doing calibration on transmitters you verify HAC integrity, PMs on packaged eqt would be the same etc.
Also, do you keep a register of classified eqt? I know in the IEC world that is a requirement.
Also, do you keep a register of classified eqt? I know in the IEC world that is a requirement.