timothy.collins
Member
- Location
- Florida
The Situation:
A facility wishes to have a emergency generator installed (1.1Mg). The installation also includes two Auto Transfer switches. The facility is fed with two large transformers, each from a different riser pole. These transformers feed into a mechanical room to an A bus and B bus with a Tie Breaker. This allows for the building load to be carried by either transformer (max 2000amps) This facility currently has no backup capability ie., Generator. From the A & B breakers, power is then distributed to multiple distribution panels with no reasonable access to break into the load side of the A & B bus to place in the two transfer switches. However, with removal and relocation of the transformers the switches can be placed over the load conductors conduits going into the building, allowing for the automatic transfer of failed power from either transformer. Are there any provisions in the NEC that would allow this installation. Under artical 230-82 it lists equipment permitted ahead (supply side) of the service disconnect. However, in the handbook it does include this statement: Systems such as emergency, fire alarms, fire pumps, standby power and sprinkler systems are permitted to be connected ahead of the normal service disconnecting means if such systems are provided with a seperate disconnecting means and overcurrent protection. Please advise if this applies to my situation... Thx for your time
[ February 27, 2003, 03:52 PM: Message edited by: timothy.collins ]
A facility wishes to have a emergency generator installed (1.1Mg). The installation also includes two Auto Transfer switches. The facility is fed with two large transformers, each from a different riser pole. These transformers feed into a mechanical room to an A bus and B bus with a Tie Breaker. This allows for the building load to be carried by either transformer (max 2000amps) This facility currently has no backup capability ie., Generator. From the A & B breakers, power is then distributed to multiple distribution panels with no reasonable access to break into the load side of the A & B bus to place in the two transfer switches. However, with removal and relocation of the transformers the switches can be placed over the load conductors conduits going into the building, allowing for the automatic transfer of failed power from either transformer. Are there any provisions in the NEC that would allow this installation. Under artical 230-82 it lists equipment permitted ahead (supply side) of the service disconnect. However, in the handbook it does include this statement: Systems such as emergency, fire alarms, fire pumps, standby power and sprinkler systems are permitted to be connected ahead of the normal service disconnecting means if such systems are provided with a seperate disconnecting means and overcurrent protection. Please advise if this applies to my situation... Thx for your time
[ February 27, 2003, 03:52 PM: Message edited by: timothy.collins ]