DanZ
Senior Member
Hey guys,
We?re looking at the possibility of installing a new generator for an existing dentist office. I was wondering if you could tell me what would be an acceptable installation. Could we just have one transfer switch before the existing panel, or would we have to run a separate panel that only has lighting, treatment room receptacles and other ?essential? equipment?
We're on the 2008 NEC. I've looked at 517, and found the figures 517.30, but I'm stuck in the "Why do we have to do it that way" argument with the higher ups. :roll:
I suggested sizing a generator that would equal the calculated output of the panel, but I'm not sure if we could use the existing panel, or if we would have to break it down in to a panel and a sub panel with separate transfer switches.
Any help or advice would be greatly appreciated!:grin:
We?re looking at the possibility of installing a new generator for an existing dentist office. I was wondering if you could tell me what would be an acceptable installation. Could we just have one transfer switch before the existing panel, or would we have to run a separate panel that only has lighting, treatment room receptacles and other ?essential? equipment?
We're on the 2008 NEC. I've looked at 517, and found the figures 517.30, but I'm stuck in the "Why do we have to do it that way" argument with the higher ups. :roll:
I suggested sizing a generator that would equal the calculated output of the panel, but I'm not sure if we could use the existing panel, or if we would have to break it down in to a panel and a sub panel with separate transfer switches.
Any help or advice would be greatly appreciated!:grin:
