Guys, Here you go 1961 era, Multifamily dwelling. 400 A Zinsco Service the EGC goes thru 1" ridgid to Bldg. supply water line and is clamped. problem is the supply line is 3" pvc below grade no 10' contact with soil. so.. add a rod sized to service and gec , 250.66 says 1/0 copper. Does this have to be one piece from service, to pipe, to rod, or can I clamp to pipe and go to Rod with Proper Clamp of Course!!