We have been working with an integrator installing ultrasonic heads in wastwater manholes to measure the amount of wastewater being returned to the city for treatment.
The heads are low voltage and intrinsically safe and are served by a factory installed jacketed cable from the manhole to the recording instrument in the nearest building.
Our inspector wanted to see a sticker or other indication that a NRTL had certified these flow meters.
My question: Where in the NEC is this required?
The factory people were incredulous...apparently they had not had anything like this happen before.
The heads are low voltage and intrinsically safe and are served by a factory installed jacketed cable from the manhole to the recording instrument in the nearest building.
Our inspector wanted to see a sticker or other indication that a NRTL had certified these flow meters.
My question: Where in the NEC is this required?
The factory people were incredulous...apparently they had not had anything like this happen before.