electro7
Senior Member
- Location
- Northern CA, US
- Occupation
- Electrician, Solar and Electrical Contractor
A plan checker in a jurisdiction I am working in gave a correction notice that said insulation piercing connectors need to be field verified by a UL listed engineer. I was wondering if anybody else has encounteted this? Is that normal? Its the first time I have been called on this. It is for a feeder tap installation for solar downstream from the main breaker.
Would the field engineer witness the torque test on the connectors?
I made a correction to hopefully appease him, using polaris taps instead. But I wanted to get some opinions.
Thanks ahead of time.
Sent from my SM-N960U using Tapatalk
Would the field engineer witness the torque test on the connectors?
I made a correction to hopefully appease him, using polaris taps instead. But I wanted to get some opinions.
Thanks ahead of time.
Sent from my SM-N960U using Tapatalk