Any ballpark estimates would be helpful. The job consists of:
* Bringing power from a generator 200' to a MLO panel at the shore.(Disconnect at the generator, direct bury #4 USE Al to the panel)
The following circuits from the panel
- 3 lights on 1 switch on pier walkway approximately 80"
- 2 individually switched lights in boathouse approximately 100'
- 2 3/4HP motors for jet ski lifts approximately 80'
- 2 3/4 HP motors for boat lift approximately 100'
Pier builder would like all the wiring in UF. There is currently nothing on this property.
My price $4550
Thanks in advance for all responses
* Bringing power from a generator 200' to a MLO panel at the shore.(Disconnect at the generator, direct bury #4 USE Al to the panel)
The following circuits from the panel
- 3 lights on 1 switch on pier walkway approximately 80"
- 2 individually switched lights in boathouse approximately 100'
- 2 3/4HP motors for jet ski lifts approximately 80'
- 2 3/4 HP motors for boat lift approximately 100'
Pier builder would like all the wiring in UF. There is currently nothing on this property.
My price $4550
Thanks in advance for all responses