brantmacga
Señor Member
- Location
- Georgia
- Occupation
- Former Child
See pic for reference .....
The schedule calls for panel M to be MLO; I ordered as MCB being that they are requiring shunt trip.
Would the 600A DPDT switch shown be required to have fuses? The secondary is underground from a padmount, and then will go under the slab to panel M.
Square D doesn't make a fusible 600A DPDT switch so I stopped the shipment.
If this switch weren't there, fuses wouldn't be required. Does this situation change that?
Thanks
Sent from my iPhone using Tapatalk
The schedule calls for panel M to be MLO; I ordered as MCB being that they are requiring shunt trip.
Would the 600A DPDT switch shown be required to have fuses? The secondary is underground from a padmount, and then will go under the slab to panel M.
Square D doesn't make a fusible 600A DPDT switch so I stopped the shipment.
If this switch weren't there, fuses wouldn't be required. Does this situation change that?
Thanks
Sent from my iPhone using Tapatalk