I put this in here to get an idea from owners/managers on how to handle this issue. I am a licensed Master in NV, but moved to CA because of a very complicated family situation. I have yet to get my card transferred here due to needing paperwork from SSA and the COVID crap shutting them down.
i just started a new job this week and I worked with a guy yesterday whose work was pretty but he has no concept of code and theory. The company is a big outfit and I have no relationship with my direct supervisor but a little more with his boss cause he hired me. But my direct supervisor is friends w the guy I worked with yesterday.
We did an installation yesterday that is an inspectors nightmare if they know what they are looking for, if no the work is very clean and they would think it’s professional cause it looks good. Violations include conduit fill, undersized feeders due to ampacity corrections, undersized branch circuits due to ampacity, oversized breakers(when originally installed), and much more but these concern me the most. They guy didn’t even look at the prints and relocated everything to a sub when they weren’t supposed to go there, complete disaster. I told the guy many different times that it was wrong and a fire hazard but he wouldn’t listen because I’m new and younger. Instead of looking at the NEC he said he called someone and they told him what I said was wrong. I refused to tie it into the breakers and land lugs because I new it was wrong.
My question isn’t whether I say something or not, cause I am. But do I bring it to my direct supervisor or the main supervisor? And how do I approach it, cause I don’t want to create problems but it needs to be fixed before it burns down that house
i just started a new job this week and I worked with a guy yesterday whose work was pretty but he has no concept of code and theory. The company is a big outfit and I have no relationship with my direct supervisor but a little more with his boss cause he hired me. But my direct supervisor is friends w the guy I worked with yesterday.
We did an installation yesterday that is an inspectors nightmare if they know what they are looking for, if no the work is very clean and they would think it’s professional cause it looks good. Violations include conduit fill, undersized feeders due to ampacity corrections, undersized branch circuits due to ampacity, oversized breakers(when originally installed), and much more but these concern me the most. They guy didn’t even look at the prints and relocated everything to a sub when they weren’t supposed to go there, complete disaster. I told the guy many different times that it was wrong and a fire hazard but he wouldn’t listen because I’m new and younger. Instead of looking at the NEC he said he called someone and they told him what I said was wrong. I refused to tie it into the breakers and land lugs because I new it was wrong.
My question isn’t whether I say something or not, cause I am. But do I bring it to my direct supervisor or the main supervisor? And how do I approach it, cause I don’t want to create problems but it needs to be fixed before it burns down that house