Adamjamma
Senior Member
- Location
- Jamaica and london
Ok. Jamaica has announced again that it is planning to adopt the International Building codes and once the law is finally, after 15 years of drafts, signed in, all adoptions in future will be within one code cycle, for any updates to code, based upon Caribbean Uniform, and Canadian codes, so for the industry to start looking at US codes, specifically Puerto Rico and California and Florida codes, for hints of how to proceed due to hurricanes and other items. This is a great deal for Jamaica sa they have been supposed to redo the building codes since 2002..lol...
Great priority, right!
But, based upon that, with the only other addition being the use of Metric sizings as they are already in common use... so still a mix of NEC and BS 7671-...
If I have a 200 amp Meter, running into a post mounted outdoor cutoff switch, lockable... then through underground feeder to a main Breaker Panel , which is then subfed to other panels on other floors, which is what we have to do under current code...
I treat the cable from the meter to the cutoff as 80 percent .. as a service
then do I treat the feed from the cutoff to first panel as service- 80 percent, or as feeder- 100 percent?
and of course the rest get treated as 100 percent but distances are short--twelve feet or less normally... so not too bad...
Still getting confused by the feeder service changes..lol
I know that if I only used a main breaker in the first panel, this is then a service entrance so whole distance is rated as a service at 80 percent.. just confused about adding a breaker or service cutoff at the pole... as there has been talk that any home in Jamaica that has more than 10 solar panels will require it...
Great priority, right!
But, based upon that, with the only other addition being the use of Metric sizings as they are already in common use... so still a mix of NEC and BS 7671-...
If I have a 200 amp Meter, running into a post mounted outdoor cutoff switch, lockable... then through underground feeder to a main Breaker Panel , which is then subfed to other panels on other floors, which is what we have to do under current code...
I treat the cable from the meter to the cutoff as 80 percent .. as a service
then do I treat the feed from the cutoff to first panel as service- 80 percent, or as feeder- 100 percent?
and of course the rest get treated as 100 percent but distances are short--twelve feet or less normally... so not too bad...
Still getting confused by the feeder service changes..lol
I know that if I only used a main breaker in the first panel, this is then a service entrance so whole distance is rated as a service at 80 percent.. just confused about adding a breaker or service cutoff at the pole... as there has been talk that any home in Jamaica that has more than 10 solar panels will require it...