Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
So something I have a hard time figuring sometimes is the amount of time to figure a NON WORKING foreman on a job.
What I mean is that say a GC says the schedule is 1-1/2 years then I figure my crew size and look at total hours sometimes it comes out to be less of a duration than the GC is saying the job is. In this case it may be 14 months. But I'm not sure if the job will still require us to be on the job for the entire duration the GC is providing, even if smaller crew, but then I need to make sure I account for the NON working foreman for the entire duration along with other monthly expenses such as trailer, storage container etc.
How does one approach this for the INDIRECT costs(supervision, trailer etc.) just always figure whatever schedule the GC provides?
Thinking there's more to figuring this out than that.
What I mean is that say a GC says the schedule is 1-1/2 years then I figure my crew size and look at total hours sometimes it comes out to be less of a duration than the GC is saying the job is. In this case it may be 14 months. But I'm not sure if the job will still require us to be on the job for the entire duration the GC is providing, even if smaller crew, but then I need to make sure I account for the NON working foreman for the entire duration along with other monthly expenses such as trailer, storage container etc.
How does one approach this for the INDIRECT costs(supervision, trailer etc.) just always figure whatever schedule the GC provides?
Thinking there's more to figuring this out than that.
