I just put a bid in for a second floor addition:
3 bdrms w/walkin closets
Tv room - not a media/mini cinema,
master bath w/jacuzzi/hydro massage
laundry room
12' "common" hallway between bdrms/laundry
Here's what is being added:
22 switches (13-SP; 8 3way;,1 4way)
32 fixtures (boxed, fixture hung, includes smoke heads at 11 locations, 4 CF boxes(no fans ~ for future), 2 F/L combos in bath, 2 sconces in bath, 2 WP recessed cans in bath)
34 recept. (5 GFCIs, 2 of which will be under eaves for xmas lights)
1 outdoor fixture (boxed + hung)
1 Jacuzzi wiring
2 AC units~ comp & handler units (3 ton each? @ 1 ton/550 sq. ft)
1 200A service (OH, 40" RNC, CU conductors, Square D QO)
1 100A sub panel (Square D QO)
Permit (fee)
-At this point, customer is responsible for purchasing ALL fixtures and bulbs.
-NO LV (T-stats, tele, cable/SAT,intercom, etc) is included at this point. I'll try and sell that wiring along with a central vac before the rough is started.(Any other "sales" in mind? )
-All branch circuits will be NM, sub panel will be AC riser cable.
- laundry, stove, etc is gas
-Job is roughly 1 hour/35 miles from my "base (each way)...supply house is conveniently located on way out of my town (almost).
Some of the SD's (6 of them) will be added to existing 1st flr and basement areas (stairs, 1 bdrm, basement, etc)...which will be "habited" during this process.
Sq. Ft. addition is roughly 1500 (foot print matches existing). No cathederal ceilings.
This is in northern NJ.
I don't think there is anything else I can say...I haven't even physically seen the location myself.
Any "ball park" numbers on this one?
3 bdrms w/walkin closets
Tv room - not a media/mini cinema,
master bath w/jacuzzi/hydro massage
laundry room
12' "common" hallway between bdrms/laundry
Here's what is being added:
22 switches (13-SP; 8 3way;,1 4way)
32 fixtures (boxed, fixture hung, includes smoke heads at 11 locations, 4 CF boxes(no fans ~ for future), 2 F/L combos in bath, 2 sconces in bath, 2 WP recessed cans in bath)
34 recept. (5 GFCIs, 2 of which will be under eaves for xmas lights)
1 outdoor fixture (boxed + hung)
1 Jacuzzi wiring
2 AC units~ comp & handler units (3 ton each? @ 1 ton/550 sq. ft)
1 200A service (OH, 40" RNC, CU conductors, Square D QO)
1 100A sub panel (Square D QO)
Permit (fee)
-At this point, customer is responsible for purchasing ALL fixtures and bulbs.
-NO LV (T-stats, tele, cable/SAT,intercom, etc) is included at this point. I'll try and sell that wiring along with a central vac before the rough is started.(Any other "sales" in mind? )
-All branch circuits will be NM, sub panel will be AC riser cable.
- laundry, stove, etc is gas
-Job is roughly 1 hour/35 miles from my "base (each way)...supply house is conveniently located on way out of my town (almost).
Some of the SD's (6 of them) will be added to existing 1st flr and basement areas (stairs, 1 bdrm, basement, etc)...which will be "habited" during this process.
Sq. Ft. addition is roughly 1500 (foot print matches existing). No cathederal ceilings.
This is in northern NJ.
I don't think there is anything else I can say...I haven't even physically seen the location myself.
Any "ball park" numbers on this one?