Can you provide or share the Kohler information/documentI am the big Kohler fish in a very small market. Ask what you would like.
You are correct you are supposed to run power and signal in different conduits. I almost always run the main gen power and the battery circuit in the same large conduit though.
All of their owner/installation manuals are freely available on their web site. We don't really know what specific model you are working with.Can you provide or share the Kohler information/document
They were hired by the customer. They were also supposed to set the generator (1800lbs) but only got it half way there before they started tearing up the shrubbery with a telehandler. They got run off, and I brought in a trailer and four wheeler to get it the rest of the way. I built the trailer specifically for generators, but not one this big!I would have made them do it over, or don't pay them.
And, maybe, next time, stake the four corner locations.
I am the big Kohler fish in a very small market. Ask what you would like.
You are correct you are supposed to run power and signal in different conduits. I almost always run the main gen power and the battery circuit in the same large conduit though.
Most electricians do not think that hard about this issue. The 2 separate conduits just usually terminate in the same gutter as everything else. I'm not saying it's right. But with 600 volt THHW and functionally associated control conductors, it's not a real issue.How would you separate conduits when you have 2 or 3 ATS same generator? You just nipple across? Most of the time they are installed with gutter to rough in all 3. Do you know if they need to be directly tied ATS? Just asking this has become an issue with running LV through gutter then ATS even with divider.
Kohler doesn’t like splices in the transferswitchs either, at least the feeds and load conductors.
Our local Kohler dealer would turn us down on commercial job commissions if there was splices. I had to splice the neutral on the last one because the existing was too short. The start up tech fussed about it, but went ahead and signed off.I've never heard or read that. The home transfer switches are too small to do much comfortably though.
It may be just one of Nixon Power requirements. They had that requirement for many years.Well he might have made it up, because it's not in any book I know of.
You are right but the Kohler tech commissioning system does. They want us to go from generator directly into ATS and not through gutter. I'm mostly asking what alternative or anyone experience this issue and a remedy. They do not want comm and power same conduit enclosure until it reaches ATSMost electricians do not think that hard about this issue. The 2 separate conduits just usually terminate in the same gutter as everything else. I'm not saying it's right. But with 600 volt THHW and functionally associated control conductors, it's not a real issue.