Hey folks, I have a few general questions regarding pricing for a project. I would appreciate any advice.
For example, lets say I have a project that will take a total of 10 - 1 man hours. I have 2 guys for the job, not including myself. The job is now 5 total hours. Let's say their hourly rate is $20 each and my company hourly rate is $100 per hour.
Would I charge the $100-per-hour to the 10 - 1 man hours? or to the 5 total hours?
Would the total hourly rate for labor for the entire project be (($20x2x5=$200)+($100x10))=$1200?
For example, lets say I have a project that will take a total of 10 - 1 man hours. I have 2 guys for the job, not including myself. The job is now 5 total hours. Let's say their hourly rate is $20 each and my company hourly rate is $100 per hour.
Would I charge the $100-per-hour to the 10 - 1 man hours? or to the 5 total hours?
Would the total hourly rate for labor for the entire project be (($20x2x5=$200)+($100x10))=$1200?