- Location
- Tennessee NEC:2017
- Occupation
- Semi-Retired Electrician
Let's say a job calls for 30 man hours per a labor unit estimate. Assuming it would take 30 hours for one man. Now if there were to be three men, two of them with same capabilities and one slightly less. Slightly less meaning lifting, climbing, etc.
Would the hours to complete the job with three men be 1/3 of the hours vs one man?
Or would it be somewhere between 1/3 and 1/2?
Edit: The last question would also assume the two could do it in half the time. Would that be correct or would that be slightly more than half?
Would the hours to complete the job with three men be 1/3 of the hours vs one man?
Or would it be somewhere between 1/3 and 1/2?
Edit: The last question would also assume the two could do it in half the time. Would that be correct or would that be slightly more than half?
Last edited: