John McKellar
Member
I am powering a lift station controller that has two 80amp breakers ( one for each pump) and a 10 amp breaker (for the controller) inside the controller enclosure. The electrical panel that will feed the controller is inside the building and is about 150 feet away. Will I be required to provide a disconnect switch before the the controller (right beside it)?