cdcengineer
Senior Member
We are proposing a line-side (ahead of service disconnect) tap for a solar PV interconnection. The NEC allows this per 230.91 and 240.21. I was wondering though, the tap rule for taps shorter than 10' long still requires that the rating of the overcurrent protection on the line side of the tap does not exceed 10 times the ampacity of the tap conductor. In this case, there really is no overcurrent protection (aside from bayonet fusing on the utility primary) ahead of the tap. Our service disconnect is 1200 Amps at 480V, 3-Phase.
Input anyone?