My answers are yes and yes, in that order.
When calculating the load for each building, you treat it as though the others did not exist. When calculating the service that powers all four buildings, you treat them as one large building. With the available demand factors, what this accomplishes is giving you a total service load that is lower than the sum of the four building loads.