I set up to bond csst where it enters into the building and is changed to rigid pipe then back to yellow csst
The existing gas meter was going to be relocated to that location outside the building.
Long story short. They relocated the existing meter a few feet from where it was and the plumber took exterior blk csst to go from the meter, under a deck to tie into where the new location was to be.
Should I bond at the original location I was going to, or at the existing (new) location of the meter after the meter , or ???? After the meter AND jump to where it comes out of the building as originally laid out??
(Exterior) Under ground > pipe - meter- pipe > black csst (under deck ) > pipe (enters building) > yellow csst (interior where I originally planned on placing ground clamp)
Thank you
The existing gas meter was going to be relocated to that location outside the building.
Long story short. They relocated the existing meter a few feet from where it was and the plumber took exterior blk csst to go from the meter, under a deck to tie into where the new location was to be.
Should I bond at the original location I was going to, or at the existing (new) location of the meter after the meter , or ???? After the meter AND jump to where it comes out of the building as originally laid out??
(Exterior) Under ground > pipe - meter- pipe > black csst (under deck ) > pipe (enters building) > yellow csst (interior where I originally planned on placing ground clamp)
Thank you