We are bidding an underground communications duct bank, the plans call for
(4) 3/4" inner ducts to be installed in a 4" pvc conduit. Question, What would the labor hours be for installation per 1000 feet?
No, feeding into the belled end, and pulling toward the non-belled end, of each length eliminates that snag.Always pull towards the bell end of the pipe first, this will help eliminate snags.
No, feeding into the belled end, and pulling toward the non-belled end, of each length eliminates that snag.
Draw it.