I need to install in a multifamily property a secondary dedicated service for 13 L2 E.V. Chargers; we require to install 400 amps - 120-208v 3 phase service; the plan is asking for a 1-0 E.G.C. connected to the main cold water pipe and two ground rods; the existing service feeding the apartments has the same grounding method; my question is, Could I install a separate grounding method, or connect it to the existing one? I plan to run a 1-0 E.G.C. from the meter box and terminate to the first existing ground rod, but I am not sure it will be acceptable; the project is in Santa Monica CA; building inspectors are not too helpful in this City. Thank you
 

tom baker

First Chief Moderator
Staff member
Please update your occupation as to your relation to the electrical industr. When your profile is updated send message to any moderator
 