bonding jumper
Senior Member
Dear Forumers,
I am an Electrical Designer and frequently have to install additional loads onto existing building services after the service switch. I would like to ask for input on a contradiction between the utility (Con Edison) and the NEC 25' Tap rule. The 25' tap rule states that your tap must terminate your tap conductors into an overcurrent protection device. I see frequently a service switch feeding a copper bus in a trough. Then tap conductors taken from that copper bus to feed a meter that is greater than 10' of conductor from the bus, then from the meter to the overcurrent protection device. Is there some exception that I am missing that permits this? I can say conservitively that this happens in 30% of all building in nyc. Thanks.
Edit: I also find it disturbing that if I wish to add a single disconnect from that bus after the service switch, I am required to comply with the NEC tap rules. But however, if I decided to tap the service bus, before the service switch, I have absolutely no tap rule to abide by and can run the conductors any desired legnth as long as my new disconnect switch is "service rated" and grouped with the other service switches. Thanks in advance.
[ July 16, 2004, 12:19 PM: Message edited by: bonding jumper ]
I am an Electrical Designer and frequently have to install additional loads onto existing building services after the service switch. I would like to ask for input on a contradiction between the utility (Con Edison) and the NEC 25' Tap rule. The 25' tap rule states that your tap must terminate your tap conductors into an overcurrent protection device. I see frequently a service switch feeding a copper bus in a trough. Then tap conductors taken from that copper bus to feed a meter that is greater than 10' of conductor from the bus, then from the meter to the overcurrent protection device. Is there some exception that I am missing that permits this? I can say conservitively that this happens in 30% of all building in nyc. Thanks.
Edit: I also find it disturbing that if I wish to add a single disconnect from that bus after the service switch, I am required to comply with the NEC tap rules. But however, if I decided to tap the service bus, before the service switch, I have absolutely no tap rule to abide by and can run the conductors any desired legnth as long as my new disconnect switch is "service rated" and grouped with the other service switches. Thanks in advance.
[ July 16, 2004, 12:19 PM: Message edited by: bonding jumper ]