hacim23
Journeyman Electrician
- Location
- washington, DC
- Occupation
- Electrician
Per design drawings we have left the MBJ at the MB of the switchboards and not in the XFMR. Just recently one inspector is saying that with the XFMR being outside that the MBJ is required to there in the XFMR and not inside at the first disconnecting means. I've been looking around in 250.30 and cannot find anything saying that this is a requirement. Take'er away......