I have been using Caddy MCS series mc support brackets on jobs for years. I now have an inspector who considers this bundling. Even though they comply with 310.15 to eliminate bundling/derating issues. There are less than 20 current carrying conductors in each bracket and the brackets are 4 feet apart. The cables in the middle are loose (not tied) and in the hangers they only touch each other in 2 spots. My interpretation of bundling is if they are tied together tightly every 24" that would be bundling even though nobody seems to care if you run 6 cables through a hole in a stud every 16". This inspector says there needs to be space between all cables (cant tell me how much space)
I know everybody interprets the NEC in a different way but Am I missing something?