Hello,
I am working on a design project for a new MCC that as 1200 A main CB. I've created a preliminary load calculation using continuous (125% of Amp rating) and noncontinous (100% of Amp rating) loads and am at 1220 A total. As the process will not require all equipment to be started all at the same time, would the 20A over the main CB rating be acceptable or does NEC code not allow an overages in load calculations?
I am working on a design project for a new MCC that as 1200 A main CB. I've created a preliminary load calculation using continuous (125% of Amp rating) and noncontinous (100% of Amp rating) loads and am at 1220 A total. As the process will not require all equipment to be started all at the same time, would the 20A over the main CB rating be acceptable or does NEC code not allow an overages in load calculations?